United States › Grid › Interconnection queues › Tennessee

BATTERY STORAGE · SOUTHEAST

Battery storage project 587, Hawkins County

Battery storage project 587, Hawkins County is a 225 MW battery storage request in interconnection study in the Southeast interconnection queue, in Hawkins County, Tennessee, connecting to Tennessee Valley Authority.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
587
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tennessee Valley Authority
Connection point (POI)
Phipps Bend 500 kV TL
Location
Hawkins County, Tennessee
Technology
Battery: 225 MW
Total requested
225 MW
Study phase
Facility Study
Queue status
Active
Entered queue
11 October 2023
Proposed online date
March 2029

Location

Marker shows the centre of Hawkins County; the queue data does not give exact sites.

Power plants in Tennessee · Transmission lines in Tennessee

Other requests in Hawkins County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem