United States › Grid › Interconnection queues › South Carolina
SOLAR · SOUTHEASTSolar project 957146, Newberry County
Solar project 957146, Newberry County is a 200 MW solar request in interconnection study in the Southeast interconnection queue, in Newberry County, South Carolina, connecting to Duke Energy Carolinas.
- PlanningQueued Jun 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 957146
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Carolinas
- Connection point (POI)
- CHAMPION
- Location
- Newberry County, South Carolina
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- Phase 3 Cluster Study - Study Complete
- Queue status
- Active
- Entered queue
- 27 June 2024
Location
Marker shows the centre of Newberry County; the queue data does not give exact sites.
Power plants in South Carolina · Transmission lines in South Carolina
Other requests in Newberry County
- Solar project 569164, Newberry CountySolar · 70.7 MW · in study
- Gas project 69, Newberry CountyGas · 1,212 MW · withdrawn
- Solar project 20171018001, Newberry CountySolar · 100 MW · withdrawn
- Solar + storage project 169, Newberry CountySolar + storage · 100 MW · withdrawn
- Solar project 67, Newberry CountySolar · 100 MW · withdrawn
- Battery storage project 957261, Newberry CountyBattery storage · 100 MW · withdrawn
- Solar project 22142, Newberry CountySolar · 79.8 MW · withdrawn
- Solar project 22084, Newberry CountySolar · 79.8 MW · withdrawn
- Solar project 53, Newberry CountySolar · 75.0 MW · withdrawn
- Solar project 917941, Newberry CountySolar · 74.9 MW · withdrawn
- Other project 29, Newberry CountyOther · 55.9 MW · withdrawn
- Solar project 22082, Newberry CountySolar · 52.1 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem