United States › Grid › Interconnection queues › Missouri
ONSHORE WIND · SOUTHEASTOnshore wind project GI-61, Nodaway County
Onshore wind project GI-61, Nodaway County is a 230 MW onshore wind request with a signed interconnection agreement in the Southeast interconnection queue, in Nodaway County, Missouri, connecting to Associated Electric Cooperative, Incorporated.
Queue statusConsented
- PlanningQueued May 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2019 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GI-61
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Associated Electric Cooperative, Incorporated
- Connection point (POI)
- Maryville 161 kV
- Location
- Nodaway County, Missouri
- Technology
- Wind: 230 MW
- Total requested
- 230 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 3 May 2017
- Proposed online date
- December 2019
Location
Marker shows the centre of Nodaway County; the queue data does not give exact sites.
Other requests in Nodaway County
- Onshore wind project GI-53, Nodaway CountyOnshore wind · 238 MW · agreement signed
- Gas project ERAS-2025-007, Nodaway CountyGas · 451 MW · in study
- Gas project ERAS-2025-013, Nodaway CountyGas · 451 MW · in study
- Onshore wind project J611, Nodaway CountyOnshore wind · 110 MW · built
- Gas project GEN-2024-053, Nodaway CountyGas · 451 MW · withdrawn
- Gas project GEN-2024-028, Nodaway CountyGas · 451 MW · withdrawn
- Onshore wind project GEN-2006-017, Nodaway CountyOnshore wind · 300 MW · withdrawn
- Solar project GEN-2018-022, Nodaway CountySolar · 300 MW · withdrawn
- Onshore wind project GI-67, Nodaway CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project J346, Nodaway CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project J311, Nodaway CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project J1024, Nodaway CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem