SOLAR Β· SPP

Solar project GEN-2018-022, Nodaway County

Solar project GEN-2018-022, Nodaway County is a 300 MW solar request withdrawn in the SPP interconnection queue, in Nodaway County, Missouri, connecting to GMO.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2018 (completed)
  2. Withdrawn / abandonedMar 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingJul 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-022
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
GMO
Connection point (POI)
Mullen Creek 345kV Substation
Location
Nodaway County, Missouri
Technology
Solar: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
25 May 2018
Proposed online date
July 2025
Came online
July 2025
Withdrawn
March 2024

Location

Marker shows the centre of Nodaway County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Nodaway County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem