ONSHORE WIND · MISOOnshore wind project J611, Nodaway County
Onshore wind project J611, Nodaway County is a 110 MW onshore wind request built and operating in the MISO interconnection queue, in Nodaway County, Missouri.
Request details
- Queue ID
- J611
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Clarinda - Merryville 161kV tap
- Location
- Nodaway County, Missouri
- Technology
- Wind: 110 MW
- Total requested
- 110 MW
- Study phase
- GIA
- Queue status
- Operational
- Entered queue
- 9 May 2016
- Agreement signed
- 18 December 2019
- Proposed online date
- October 2020
- Came online
- October 2020
Location
Marker shows the centre of Nodaway County; the queue data does not give exact sites.
Other requests in Nodaway County
- Onshore wind project GI-53, Nodaway CountyOnshore wind · 238 MW · agreement signed
- Onshore wind project GI-61, Nodaway CountyOnshore wind · 230 MW · agreement signed
- Gas project ERAS-2025-007, Nodaway CountyGas · 451 MW · in study
- Gas project ERAS-2025-013, Nodaway CountyGas · 451 MW · in study
- Gas project GEN-2024-053, Nodaway CountyGas · 451 MW · withdrawn
- Gas project GEN-2024-028, Nodaway CountyGas · 451 MW · withdrawn
- Onshore wind project GEN-2006-017, Nodaway CountyOnshore wind · 300 MW · withdrawn
- Solar project GEN-2018-022, Nodaway CountySolar · 300 MW · withdrawn
- Onshore wind project GI-67, Nodaway CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project J346, Nodaway CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project J311, Nodaway CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project J1024, Nodaway CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem