BATTERY STORAGE · SOUTHEAST

Battery storage project IC-1187, Wilkinson County

Battery storage project IC-1187, Wilkinson County is a 220 MW battery storage request with a signed interconnection agreement in the Southeast interconnection queue, in Wilkinson County, Georgia, connecting to Southern Company.

Queue statusConsented
  1. PlanningQueued Oct 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
IC-1187
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Gordon Substation 115 kV Bus
Location
Wilkinson County, Georgia
Technology
Battery: 220 MW
Total requested
220 MW
Service type
Energy only (ERIS)
Study phase
GIA Executed; NTP Pending
Queue status
Active
Entered queue
26 October 2023
Proposed online date
September 2027

Location

Marker shows the centre of Wilkinson County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Wilkinson County