United States › Grid › Interconnection queues › Georgia
SOLAR · SOUTHEASTSolar project IC-1088, Lee County
Solar project IC-1088, Lee County is a 200 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Lee County, Georgia, connecting to Southern Company.
Queue statusConsented
- PlanningQueued Nov 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- IC-1088
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- North Americus - Palmyra 230 kV Line
- Location
- Lee County, Georgia
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 7 November 2022
- Proposed online date
- June 2027
Location
Marker shows the centre of Lee County; the queue data does not give exact sites.
Other requests in Lee County
- Gas project 25-IC-1320B, Lee CountyGas · 111 MW · in study
- Walton Discover (aka Goat Rock)Gas · 150 MW · built
- SR DeSoto ISolar · 138 MW · built
- Solar project IC-705, Lee CountySolar · 200 MW · withdrawn
- Solar project IC-704, Lee CountySolar · 200 MW · withdrawn
- Solar project IC-516, Lee CountySolar · 95.0 MW · withdrawn
- Solar project IC-517, Lee CountySolar · 75.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem