United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA (2021 requests) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown27073.3 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

270 requests · page 3 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Geothermal project Company LM, Lyon County
Geothermal
230 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar project GEN-2021-049, Lancaster County
Solar
225 MWAgreement signed Lancaster, NESPP Apr 2021target 2029
Allium Hybrid
Solar + storage
225 MWAgreement signed San Benito, CACAISO Apr 2021target 2030
Dorian Storage
Battery storage
214 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2034
Zeus BESS
Battery storage
214 MWAgreement signed San Joaquin, CACAISO Apr 2021target 2031
Grimes County Solar
Solar · Grimes County Solar Project, LLC
211 MWAgreement signed Grimes, TXERCOT Jan 2021target 2025
Bypass Battery Storage
Battery storage · Bypass BESS LLC
208 MWAgreement signed Fort Bend, TXERCOT Aug 2021target 2025
Erath County Solar
Solar · Erath County Solar, LLC
207 MWAgreement signed Erath, TXERCOT Mar 2021target 2029
Hoyte Solar
Solar · Milano Solar LLC
207 MWAgreement signed Milam, TXERCOT Apr 2021target 2027
Desert Jewel Storage
Battery storage
206 MWAgreement signed San Diego, CACAISO Apr 2021target 2029
Desna BESS
Battery storage · BRP Desna BESS LLC
206 MWAgreement signed Brazoria, TXERCOT Dec 2021target 2026
Ferdinand Grid BESS
Battery storage · Ferdinand Grid, LLC
206 MWAgreement signed Bexar, TXERCOT Mar 2021target 2026
Pajarita BESS
Battery storage · VESI 29 LLC
206 MWAgreement signed Cameron, TXERCOT Jan 2021target 2028
Castor BESS
Battery storage · BRP Castor BESS LLC
205 MWAgreement signed Brazoria, TXERCOT Oct 2021target 2026
Naugatuck Avenue Battery Storage
Battery storage
205 MWAgreement signed New Haven, CTISO-NE Jan 2021target 2027
Battery Storage
Battery storage
205 MWAgreement signed Washington, RIISO-NE Sep 2021target 2029
Limewood Solar
Solar + storage · Limewood Bell Renewables LLC
205 MWAgreement signed Bell, TXERCOT Apr 2021target 2026
Sahara BESS (Soho BESS)
Battery storage · ESTX-PLD-HOUSTON2
204 MWAgreement signed Brazoria, TXERCOT Dec 2021target 2026
Keys Hollow Solar Phase II SLF
Solar + storage · Keys Hollow Solar, LLC
204 MWAgreement signed Goliad, TXERCOT Jun 2021target 2028
Solar project GEN-2021-033, Franklin County
Solar
204 MWAgreement signed Franklin, ARSPP May 2021target 2028
Solar project GEN-2021-036, Little River County
Solar
204 MWAgreement signed Little River, ARSPP May 2021target 2027
Keys Hollow Solar SLF
Solar + storage · Keys Hollow Solar, LLC
204 MWAgreement signed Goliad, TXERCOT Jun 2021target 2028
Norman Street Battery Storage
Battery storage
204 MWAgreement signed Middlesex, MAISO-NE Mar 2021target 2028
Sowers Storage
Battery storage · Sowers Energy Storage LLC
204 MWAgreement signed Kaufman, TXERCOT Aug 2021target 2026
Huaso Hybrid
Solar + storage
204 MWAgreement signed Fresno, CACAISO Apr 2021target 2026
Seahawk Storage
Battery storage
204 MWAgreement signed Santa Cruz, CACAISO Apr 2021target 2029
Cougar Storage
Battery storage
204 MWAgreement signed Merced, CACAISO Apr 2021target 2030
Apache Storage
Battery storage
204 MWAgreement signed Fresno, CACAISO Apr 2021target 2029
Barton Branch IA
Battery storage · Barton Branch IA LLC
204 MWAgreement signed Robertson, TXERCOT Mar 2021target 2026
Tidwell Prairie II Batt
Battery storage · TIDWELL PRAIRIE II LLC
204 MWAgreement signed Robertson, TXERCOT Mar 2021target 2026
Fewell Solar
Solar · Fewell Solar LLC
204 MWAgreement signed Limestone, TXERCOT Aug 2021target 2027
Callisto II Energy Center
Battery storage · Callisto II Energy Center LLC
203 MWAgreement signed Harris, TXERCOT Oct 2021target 2026
Inertia Solar
Solar · Inertia Solar Project, LLC
202 MWAgreement signed Haskell, TXERCOT Feb 2021target 2029
Dodd Solar I
Solar · Forest Grove Solar LLC
202 MWAgreement signed Henderson, TXERCOT Jun 2021target 2028
Stoneridge Solar
Solar · Stoneridge Solar, LLC
202 MWAgreement signed Milam, TXERCOT Oct 2021target 2026
Dry Creek Solar I
Solar · OAK HILL SOLAR LLC
201 MWAgreement signed Rusk, TXERCOT Aug 2021target 2026
Cradle Solar
Solar · Cradle Solar LLC
201 MWAgreement signed Brazoria, TXERCOT Feb 2021target 2027
Yaupon Solar SLF
Solar · Yaupon Solar, LLC
201 MWAgreement signed Milam, TXERCOT Mar 2021target 2027
Pine Forest BESS
Battery storage · Pine Forest Hybrid I, LLC
201 MWAgreement signed Hopkins, TXERCOT May 2021target 2025
Solar + storage project J1779, Dane County
Solar + storage
200 MWAgreement signed Dane, WIMISO Sep 2021target 2027
Solar project J1571, Lenawee County
Solar
200 MWAgreement signed Lenawee, MIMISO Dec 2021target 2025
Solar + storage project Company LK, Lyon County
Solar + storage
200 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar + storage project Company LG, Lyon County
Solar + storage
200 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Solar project J1603, Otsego County
Solar
200 MWAgreement signed Otsego, MIMISO Dec 2021target 2025
Battery storage project 98, Pierce County
Battery storage
200 MWAgreement signed Pierce, WAWest Mar 2021target 2026
Battery storage project Company 197, Clark County
Battery storage
200 MWAgreement signed Clark, NVWest Mar 2021target 2024
Battery storage project 21-102, Multnomah County
Battery storage
200 MWAgreement signed Multnomah, ORWest May 2021target 2030
Juan Tabo Grid
Battery storage
200 MWAgreement signed Bernalillo, NMWest Jun 2021target 2021
Old Route 66 Power
Solar
200 MWAgreement signed Guadalupe, NMWest Jun 2021target 2024
Battery storage project 21-099, Washington County
Battery storage
200 MWAgreement signed Washington, ORWest May 2021target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)