United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESProjects with signed interconnection agreements in the USA (2021 requests) — page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Geothermal project Company LM, Lyon County Geothermal |
230 MW | Agreement signed |
| Solar project GEN-2021-049, Lancaster County Solar |
225 MW | Agreement signed |
| Allium Hybrid Solar + storage |
225 MW | Agreement signed |
| Dorian Storage Battery storage |
214 MW | Agreement signed |
| Zeus BESS Battery storage |
214 MW | Agreement signed |
| Grimes County Solar Solar · Grimes County Solar Project, LLC |
211 MW | Agreement signed |
| Bypass Battery Storage Battery storage · Bypass BESS LLC |
208 MW | Agreement signed |
| Erath County Solar Solar · Erath County Solar, LLC |
207 MW | Agreement signed |
| Hoyte Solar Solar · Milano Solar LLC |
207 MW | Agreement signed |
| Desert Jewel Storage Battery storage |
206 MW | Agreement signed |
| Desna BESS Battery storage · BRP Desna BESS LLC |
206 MW | Agreement signed |
| Ferdinand Grid BESS Battery storage · Ferdinand Grid, LLC |
206 MW | Agreement signed |
| Pajarita BESS Battery storage · VESI 29 LLC |
206 MW | Agreement signed |
| Castor BESS Battery storage · BRP Castor BESS LLC |
205 MW | Agreement signed |
| Naugatuck Avenue Battery Storage Battery storage |
205 MW | Agreement signed |
| Battery Storage Battery storage |
205 MW | Agreement signed |
| Limewood Solar Solar + storage · Limewood Bell Renewables LLC |
205 MW | Agreement signed |
| Sahara BESS (Soho BESS) Battery storage · ESTX-PLD-HOUSTON2 |
204 MW | Agreement signed |
| Keys Hollow Solar Phase II SLF Solar + storage · Keys Hollow Solar, LLC |
204 MW | Agreement signed |
| Solar project GEN-2021-033, Franklin County Solar |
204 MW | Agreement signed |
| Solar project GEN-2021-036, Little River County Solar |
204 MW | Agreement signed |
| Keys Hollow Solar SLF Solar + storage · Keys Hollow Solar, LLC |
204 MW | Agreement signed |
| Norman Street Battery Storage Battery storage |
204 MW | Agreement signed |
| Sowers Storage Battery storage · Sowers Energy Storage LLC |
204 MW | Agreement signed |
| Huaso Hybrid Solar + storage |
204 MW | Agreement signed |
| Seahawk Storage Battery storage |
204 MW | Agreement signed |
| Cougar Storage Battery storage |
204 MW | Agreement signed |
| Apache Storage Battery storage |
204 MW | Agreement signed |
| Barton Branch IA Battery storage · Barton Branch IA LLC |
204 MW | Agreement signed |
| Tidwell Prairie II Batt Battery storage · TIDWELL PRAIRIE II LLC |
204 MW | Agreement signed |
| Fewell Solar Solar · Fewell Solar LLC |
204 MW | Agreement signed |
| Callisto II Energy Center Battery storage · Callisto II Energy Center LLC |
203 MW | Agreement signed |
| Inertia Solar Solar · Inertia Solar Project, LLC |
202 MW | Agreement signed |
| Dodd Solar I Solar · Forest Grove Solar LLC |
202 MW | Agreement signed |
| Stoneridge Solar Solar · Stoneridge Solar, LLC |
202 MW | Agreement signed |
| Dry Creek Solar I Solar · OAK HILL SOLAR LLC |
201 MW | Agreement signed |
| Cradle Solar Solar · Cradle Solar LLC |
201 MW | Agreement signed |
| Yaupon Solar SLF Solar · Yaupon Solar, LLC |
201 MW | Agreement signed |
| Pine Forest BESS Battery storage · Pine Forest Hybrid I, LLC |
201 MW | Agreement signed |
| Solar + storage project J1779, Dane County Solar + storage |
200 MW | Agreement signed |
| Solar project J1571, Lenawee County Solar |
200 MW | Agreement signed |
| Solar + storage project Company LK, Lyon County Solar + storage |
200 MW | Agreement signed |
| Solar + storage project Company LG, Lyon County Solar + storage |
200 MW | Agreement signed |
| Solar project J1603, Otsego County Solar |
200 MW | Agreement signed |
| Battery storage project 98, Pierce County Battery storage |
200 MW | Agreement signed |
| Battery storage project Company 197, Clark County Battery storage |
200 MW | Agreement signed |
| Battery storage project 21-102, Multnomah County Battery storage |
200 MW | Agreement signed |
| Juan Tabo Grid Battery storage |
200 MW | Agreement signed |
| Old Route 66 Power Solar |
200 MW | Agreement signed |
| Battery storage project 21-099, Washington County Battery storage |
200 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)68 · 35.4 GW
- ERCOT (Texas)91 · 16.3 GW
- West (non-ISO utilities)55 · 11.7 GW
- ISO-NE (New England)17 · 3,473 MW
- SPP (Southwest Power Pool)19 · 3,459 MW
- Southeast (non-ISO utilities)12 · 1,908 MW
- MISO (Midcontinent)8 · 1,055 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)