Cradle Solar

Cradle Solar is a 201 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusConsented
  1. PlanningQueued Feb 2021 (completed)
  2. ConsentedMar 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0150
Grid region
ERCOT (Texas)
Developer
Cradle Solar LLC
Connection point (POI)
tap 345kV 42500 Dow - 43035 Oasis ckt 18
Location
Brazoria County, Texas
Technology
Solar: 201 MW
Total requested
201 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
4 February 2021
Agreement signed
15 March 2023
Proposed online date
February 2027

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem