United States › Grid › Interconnection queues › Florida

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Florida — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown25124.3 GW
Active in queue24.3 GW251 requests
Agreement signed860 MW7 requests
Withdrawn47276.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

251 requests · page 3 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 451, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 595, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2023target 2031
Solar project 465, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2029
Solar project 523, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2028
Solar project 358, Brevard County
Solar · FPL
74.5 MWIn study Brevard, FLSoutheast Jul 2018target 2028
Solar project 570, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2031
Solar project 121, Hillsborough County
Solar
74.5 MWIn study Hillsborough, FLSoutheast May 2025target 2027
Solar project 461, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2028
Solar project 593, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jul 2023target 2030
Solar project 434, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Mar 2022target 2027
Solar project 20
Solar
74.5 MWPaused / redesign FLSoutheast Oct 2017target 2019
Solar project 457, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 530, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2030
Solar project 513, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030
Solar project 552, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2032
Solar project 430, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Mar 2022target 2026
Solar project 455, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2031
Solar project 564, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2032
Solar project 339, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Mar 2018target 2027
Solar project 490, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jan 2023target 2029
Solar project 543, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 405, Okeechobee County
Solar · FPL
74.5 MWIn study Okeechobee, FLSoutheast Jul 2020target 2027
Solar project 471, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jul 2022target 2029
Storey Bend
Solar
74.5 MWIn study Osceola, FLSoutheast Feb 2018target 2024
Solar project 561, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jul 2023target 2030
Solar project 521, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jan 2023target 2030
Solar project 500, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 496, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2029
Solar project 460, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2026
Solar project 462, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2029
Solar project 448, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 412, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2028
Solar project 444, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2026
Solar project 459, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Apr 2022target 2026
Solar project 306, Brevard County
Solar · FPL
74.5 MWIn study Brevard, FLSoutheast Jun 2017target 2026
Solar project 406, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2020target 2027
Solar project 237, Pasco County
Solar · Florida Renewable Partners, LLC
74.5 MWIn study Pasco, FLSoutheast Jul 2018target 2021
Solar project 424D, Madison County
Solar · FPL
74.5 MWIn study Madison, FLSoutheast Aug 2021target 2027
Solar project 559, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jul 2023target 2032
Solar project 449, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2029
Solar project 333, Nassau County
Solar · FPL
74.5 MWIn study Nassau, FLSoutheast Feb 2018target 2026
Solar project 344, Baker County
Solar · FPL
74.5 MWIn study Baker, FLSoutheast May 2018target 2026
Solar project 516, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030
Solar project 550, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2032
Solar project 528, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2029
Solar project 424A, Leon County
Solar · FPL
74.5 MWIn study Leon, FLSoutheast Aug 2021target 2033
Solar project 514, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030
Solar project 544, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 446, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Apr 2022target 2028
Solar project 499, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20152025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)