Solar project 237, Pasco County

Solar project 237, Pasco County is a 74.5 MW solar request in interconnection study in the Southeast interconnection queue, in Pasco County, Florida, connecting to Duke Energy Florida.

Queue statusIn planning
  1. PlanningQueued Jul 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
237
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Florida Renewable Partners, LLC
Connection point (POI)
Trilby Substation
Location
Pasco County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
NRIS and ERIS
Study phase
System Impact Study
Queue status
Active
Entered queue
17 July 2018
Proposed online date
December 2021

Location

Marker shows the centre of Pasco County; the queue data does not give exact sites.