Gas project 109, Pasco County

Gas project 109, Pasco County is a 1,400 MW gas request withdrawn in the Southeast interconnection queue, in Pasco County, Florida, connecting to Duke Energy Florida.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2011 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
109
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Duke Energy Florida, LLC
Connection point (POI)
Anclote Substation
Location
Pasco County, Florida
Technology
Gas: 1,400 MW
Total requested
1,400 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
22 July 2011
Proposed online date
April 2016

Location

Marker shows the centre of Pasco County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Pasco County