Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 25 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GI-2024-18, Morgan County
Solar
150 MWIn study Morgan, COWest May 2024target 2027
Solar project J1155, Mississippi County
Solar
150 MWUnder construction Mississippi, ARMISO Mar 20182024
Solar project 18-11071, Larimer County
Solar
150 MWUnder construction Larimer, COWest Nov 2018target 2023
Solar project J3722, Hillsdale County
Solar
150 MWIn study Hillsdale, MIMISO Mar 2024target 2028
Whatley Solar
Solar · Invenergy
150 MWPaused / redesign Andrews, TXERCOT May 2015target 2020
Solar
Solar
150 MWAgreement signed Hartford, CTISO-NE Mar 2022target 2028
Solar project GEN-2024-282, Meade County
Solar
150 MWIn study Meade, SDSPP Mar 2025target 2030
Solar project J2501, Goodhue County
Solar
150 MWIn study Goodhue, MNMISO Sep 2022target 2024
Solar project G1001, Grant County
Solar
150 MWIn study Grant, WAWest Nov 2023target 2029
Solar project J1096, Saline County
Solar
150 MWUnder construction Saline, ILMISO Mar 2018target 2024
Big Pine Solar
Solar
150 MWAgreement signed Sussex, VAPJM Feb 2019target 2031
Solar project J2720, Yazoo County
Solar
150 MWIn study Yazoo, MSMISO Sep 2022target 2025
Solar project J2314, Liberty County
Solar
150 MWIn study Liberty, TXMISO Sep 2021target 2023
Gemstone Solar
Solar
150 MWAgreement signed Cass, MIPJM Jan 2020target 2028
Solar project J2156, Johnson County
Solar
150 MWIn study Johnson, ILMISO Jun 2022target 2024
Solar project GI-2023-170, Imperial County
Solar
150 MWIn study Imperial, CAWest Apr 2023target 2026
Nickel Spruce Solar
Solar · Nickel Spruce Solar LLC
150 MWIn study Leon, TXERCOT Jan 2023target 2027
Solar project J874, Murray County
Solar
150 MWUnder construction Murray, MNMISO Jun 2017target 2024
Solar project J1724, Laporte County
Solar
150 MWIn study Laporte, INMISO Dec 2021target 2023
Daystar Solar
Solar · Choate Solar, LLC
150 MWIn study Karnes, TXERCOT Apr 2024target 2028
Solar project GEN-2019-054, Barton County
Solar
150 MWPaused / redesign Barton, KSSPP May 2019target 2029
Wake Solar
Solar · Invenergy
150 MWPaused / redesign Crosby, TXERCOT Jul 2015target 2021
Solar project J2155, New Madrid County
Solar
150 MWIn study New Madrid, MOMISO Mar 2022target 2024
Solar project IC-1015, Mitchell County
Solar
150 MWPaused / redesign Mitchell, GASoutheast Jan 2022target 2027
Solar project J1646, Newton County
Solar
150 MWIn study Newton, INMISO Jun 2020target 2026
Brenneman Solar
Solar
150 MWIn study Macon, GASoutheast Nov 2022target 2024
Solar project J3107, Johnson County
Solar
150 MWIn study Johnson, IAMISO Oct 2025target 2025
SR Grady_SR Whigham
Solar
150 MWUnder construction Grady, GASoutheast Aug 2024target 2028
Solar project J1072, Mower County
Solar
150 MWUnder construction Mower, MNMISO Mar 2018target 2023
Solar project J1320, Branch County
Solar
150 MWAgreement signed Branch, MIMISO Apr 2019target 2025
Exie Solar
Solar · Exie Solar, LLC
150 MWAgreement signed Green, KYPJM Sep 2020target 2028
Solar project J1641, Greene County
Solar
150 MWIn study Greene, INMISO Mar 2024target 2026
Solar project GEN-2020-091, Mckenzie County
Solar
150 MWAgreement signed Mckenzie, NDSPP Apr 2020target 2029
Solar project J1638, Hancock County
Solar
150 MWIn study Hancock, KYMISO Feb 2022target 2026
Dawson Solar
Solar
150 MWIn study Terrell, GASoutheast Sep 20192022
Solar project GEN-2017-187, Terry County
Solar
150 MWAgreement signed Terry, TXSPP Nov 2017target 2026
Solar project J1388, Gibson County
Solar
150 MWAgreement signed Gibson, INMISO Apr 2019target 2024
Solar project J859, Cass County
Solar
150 MWUnder construction Cass, ILMISO Jun 2017target 2022
Solar project J986, Wood County
Solar
150 MWAgreement signed Wood, WIMISO Mar 20182023
Solar project J1750, Marquette County
Solar
150 MWUnder construction Marquette, MIMISO Apr 2022target 2026
Solar project J1744, Cumberland County
Solar
150 MWIn study Cumberland, ILMISO Apr 2022target 2027
Solar project J1651, Logan County
Solar
150 MWIn study Logan, ILMISO Jun 2020target 2023
Riverstone Solar
Solar
150 MWAgreement signed Buckingham, VAPJM Sep 2018target 2027
Solar project 278, Williamsburg County
Solar
150 MWIn study Williamsburg, SCSoutheast Jun 2024target 2028
Pilesgrove Solar Project
Solar
149 MWPaused / redesign Salem, NJPJM Sep 2018target 2027
Maroon Solar
Solar
149 MWPaused / redesign Culpeper, VAPJM Sep 2018target 2027
Solar project J818, Jefferson County
Solar
149 MWUnder construction Jefferson, WIMISO Jun 2017target 2022
Solar project 636, Elmore County
Solar · Soles Rest Solar LLC
149 MWAgreement signed Elmore, IDWest Feb 2022target 2028
Enclave Solar Energy Center
Solar
149 MWPaused / redesign Sussex, VAPJM Jan 2019target 2027
Solar project J3679, Laporte County
Solar
149 MWIn study Laporte, INMISO Apr 2024target 2028
Page 25 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)