United States › Grid › Interconnection queues › Kentucky
SOLAR · PJMExie Solar
Exie Solar is a 150 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Green County, Kentucky, connecting to EKPC.
Queue statusConsented
- PlanningQueued Sep 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AG1-354
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Developer
- Exie Solar, LLC
- Connection point (POI)
- Summershade-Green County 161 kV
- Location
- Green County, Kentucky
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Active
- Entered queue
- 30 September 2020
- Proposed online date
- October 2028
Location
Marker shows the centre of Green County; the queue data does not give exact sites.
Other requests in Green County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem