United States › Grid › Interconnection queues › North Dakota
SOLAR · SPPSolar project GEN-2020-091, Mckenzie County
Solar project GEN-2020-091, Mckenzie County is a 150 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Mckenzie County, North Dakota, connecting to BEPC.
Queue statusConsented
- PlanningQueued Apr 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2020-091
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- BEPC
- Connection point (POI)
- Patent Gate Substation 345 kV
- Location
- Mckenzie County, North Dakota
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 30 April 2020
- Proposed online date
- December 2029
Location
Marker shows the centre of Mckenzie County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Mckenzie County
- Gas project GI-1206, Mckenzie CountyGas · 125 MW · built
- Gas project GI-1204, Mckenzie CountyGas · 50.0 MW · built
- Gas project GI-1202, Mckenzie CountyGas · 50.0 MW · built
- Gas project GI-1208, Mckenzie CountyGas · 50.0 MW · built
- Gas project GEN-2020-014, Mckenzie CountyGas · 45.0 MW · built
- Solar project GEN-2021-008, Mckenzie CountySolar · 200 MW · withdrawn
- Battery storage project GEN-2024-185, Mckenzie CountyBattery storage · 199 MW · withdrawn
- Gas project GI-1304, Mckenzie CountyGas · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem