United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

GAS Β· WEST

Gas project GI-1304, Mckenzie County

Gas project GI-1304, Mckenzie County is a 100 MW gas request withdrawn in the West interconnection queue, in Mckenzie County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-1304
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Williston-Ch. Creek 230kV
Location
Mckenzie County, North Dakota
Technology
Gas: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
IAP
Queue status
Withdrawn
Entered queue
4 April 2013
Proposed online date
November 2016

Location

Marker shows the centre of Mckenzie County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Mckenzie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem