United States › Grid › Interconnection queues › Kansas
SOLAR · SPPSolar project GEN-2019-054, Barton County
Solar project GEN-2019-054, Barton County is a 150 MW solar request suspended in the SPP interconnection queue, in Barton County, Kansas, connecting to SUNC.
Queue statusPaused / redesign
- PlanningQueued May 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2019-054
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Great Bend- Circle 230kV line
- Location
- Barton County, Kansas
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SUSPENSION
- Queue status
- Suspended
- Entered queue
- 24 May 2019
- Proposed online date
- August 2029
Location
Marker shows the centre of Barton County; the queue data does not give exact sites.
Other requests in Barton County
- Battery storage project GEN-2019-068, Barton CountyBattery storage · 50.0 MW · suspended
- Onshore wind project GEN-2009-010, Barton CountyOnshore wind · 200 MW · withdrawn
- Gas project GEN-2009-014, Barton CountyGas · 151 MW · withdrawn
- Onshore wind project GEN-2009-009, Barton CountyOnshore wind · 150 MW · withdrawn
- Solar project GEN-2018-116, Barton CountySolar · 150 MW · withdrawn
- Battery storage project GEN-2019-051, Barton CountyBattery storage · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem