United States › Grid › Interconnection queues › Kansas

BATTERY STORAGE · SPP

Battery storage project GEN-2019-068, Barton County

Battery storage project GEN-2019-068, Barton County is a 50.0 MW battery storage request suspended in the SPP interconnection queue, in Barton County, Kansas, connecting to SUNC.

Queue statusPaused / redesign
  1. PlanningQueued May 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2019-068
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Great Bend - Circle 230kV line
Location
Barton County, Kansas
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SUSPENSION
Queue status
Suspended
Entered queue
24 May 2019
Proposed online date
August 2029

Location

Marker shows the centre of Barton County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Barton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem