United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2019 requests) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown589109.2 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

589 requests · page 2 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q310, Yuma County
Solar + storage
450 MWAgreement signed Yuma, AZWest Aug 2019target 2023
Buffalo Creek
Solar · Lincoln Clean Energy Development
439 MWAgreement signed Fort Bend, TXERCOT Aug 2019target 2026
Dragan Solar
Solar + storage · Hecate Comanche Solar LLC
411 MWIn study Comanche, TXERCOT Nov 2019target 2027
Solar + storage project J1263, Clark County
Solar + storage
409 MWAgreement signed Clark, ILMISO Apr 2019target 2025
Rough Hat Hybrid Solar
Solar + storage
404 MWAgreement signed Nye, NVCAISO Apr 2019target 2028
Aratina Solar Center 2
Solar + storage
400 MWAgreement signed Kern, CACAISO Apr 2019target 2026
Onshore wind project 367, Rosebud County
Onshore wind
400 MWPaused / redesign Rosebud, MTWest Sep 2019target 2022
Space City Solar
Solar · Apollo Solar Ranch, LLC
366 MWAgreement signed Wharton, TXERCOT Nov 2019target 2027
Jewelflower Storage
Battery storage
355 MWAgreement signed Santa Clara, CACAISO Apr 2019target 2029
Fighting Jays Solar
Solar · AP Solar Holdings, LLC
351 MWAgreement signed Fort Bend, TXERCOT Mar 2019target 2026
Solar + storage project Company JX, Pershing County
Solar + storage
340 MWPaused / redesign Pershing, NVWest Sep 2019target 2023
Greyhound Solar
Solar · Rockhound Solar 2, LLC dba "Greyhound Solar"
336 MWAgreement signed Ector, TXERCOT Mar 2019target 2026
Mountaineer Solar
Solar · Mustang Mountaineer Solar LLC
332 MWIn study Brown, TXERCOT Apr 2019target 2028
Pecan Prairie North
Solar · CG Leon County II LLC
321 MWAgreement signed Leon, TXERCOT Sep 2019target 2027
Hickerson Solar
Solar + storage · Hickerson Solar
311 MWAgreement signed Bosque, TXERCOT May 2019target 2025
Humidor Storage 1
Battery storage
305 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2028
Sisters Solar
Solar + storage · Oberon Solar LLC
302 MWAgreement signed Ector, TXERCOT Feb 2019target 2027
Onshore wind project 83, Meagher County
Onshore wind
300 MWAgreement signed Meagher, MTWest Mar 2019
Onshore wind project 71, Meagher County
Onshore wind
300 MWPaused / redesign Meagher, MTWest Mar 2019target 2029
Onshore wind project C007, Meagher County
Onshore wind
300 MWIn study Meagher, MTWest Mar 2019target 2022
Onshore wind project 362, Wheatland County
Onshore wind
300 MWPaused / redesign Wheatland, MTWest Apr 2019target 2022
Yellow Wood Solar Energy Center
Solar
300 MWAgreement signed Clinton, OHPJM Mar 2019target 2026
Onshore wind project J1360, Piatt County
Onshore wind
300 MWAgreement signed Piatt, ILMISO Apr 2019target 2024
Cassius Blue Solar
Solar + storage
300 MWAgreement signed Sussex, VAPJM Feb 2019target 2031
Solar + storage project 573, Power County
Solar + storage · NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Power, IDWest Nov 2019target 2027
Steward Creek Solar
Solar · Steward Creek Solar, LLC
300 MWIn study Lee, ILPJM Dec 2019target 2023
Solar project J1421, East Feliciana Parish County
Solar
300 MWUnder construction East Feliciana Parish, LAMISO Apr 2019target 2024
Battery storage project Q314, Maricopa County
Battery storage
300 MWIn study Maricopa, AZWest Sep 2019target 2022
Solar project J1410, Dane County
Solar
300 MWUnder construction Dane, WIMISO Apr 2019target 2025
Solar project J1214, Dane County
Solar
300 MWAgreement signed Dane, WIMISO Apr 2019target 2025
Nighthawk Storage
Battery storage
300 MWAgreement signed San Diego, CACAISO Apr 2019target 2026
Solar + storage project 2019-G1, Butte County
Solar + storage
300 MWIn study Butte, CAWest Aug 2019target 2027
Three Lakes Solar
Solar + storage · Three Lakes Solar LLC
300 MWIn study St. Joseph, MIPJM Sep 2019target 2022
Solar project J1308, Posey County
Solar
300 MWAgreement signed Posey, INMISO Apr 2019target 2024
Diversion Wind
Onshore wind
300 MWPaused / redesign Baylor, TXERCOT Sep 2019target 2024
Solar + storage project G0617, Sherman County
Solar + storage
300 MWIn study Sherman, ORWest Mar 2019target 2022
Onshore wind project MPC04000, Oliver County
Onshore wind
300 MWAgreement signed Oliver, NDMISO Apr 2019target 2023
Board Creek Wind
Onshore wind · Limestone Wind Project, LLC
299 MWAgreement signed Navarro, TXERCOT Apr 2019target 2026
Black Diamond Solar
Solar · Black Diamond Solar Power, LLC
299 MWIn study Christian, ILPJM Mar 2019target 2022
Monarch Creek Wind
Onshore wind · MONARCH CREEK WIND, LLC
284 MWAgreement signed Throckmorton, TXERCOT Apr 2019target 2027
Impala Flats Wind
Onshore wind · Antelope Flats Wind, LLC
282 MWIn study Lynn, TXERCOT Jan 2019target 2026
Blue Hills Wind
Onshore wind
276 MWPaused / redesign Val Verde, TXERCOT May 2019target 2026
Charolais Solar
Solar + storage · RWE Solar Development, LLC
262 MWIn study Matagorda, TXERCOT Aug 2019target 2026
Solar project IC-789, Decatur County
Solar
260 MWAgreement signed Decatur, GASoutheast Apr 2019target 2028
Solar project IC-774, Mitchell County
Solar
260 MWAgreement signed Mitchell, GASoutheast Feb 2019target 2022
Vermilion Grove Wind
Onshore wind · Vermilion Grove Wind, LLC
255 MWIn study Vermillion, INPJM Sep 2019target 2022
Onshore wind project GEN-2019-030, Ford County
Onshore wind
252 MWAgreement signed Ford, KSSPP Apr 2019target 2027
Velociraptor Solar I
Solar + storage · Greyhound Solar 2
252 MWIn study Ector, TXERCOT May 2019target 2028
Medway Grid Battery Storage
Battery storage
250 MWAgreement signed Norfolk, MAISO-NE Mar 2019target 2025
Commerce Energy Storage
Battery storage
250 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2026
Page 2 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)