Interconnection queue in the USA (2017 requests) โ€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown29251.0 GW
Active in queue51.0 GW292 requests
Agreement signed32.8 GW182 requests
Withdrawn1,258161.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

292 requests ยท page 2 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2017-164, Garfield County
Solar
250 MWAgreement signed Garfield, OKSPP Nov 20172025
Solar + storage project NC5-003, Clark County
Solar + storage
250 MWIn study Clark, NVWest Aug 2017target 2022
Solar project J829, Sullivan County
Solar
250 MWUnder construction Sullivan, INMISO Jun 2017target 2022
Solar + storage project Q252, Yuma County
Solar + storage
250 MWUnder construction Yuma, AZWest Mar 2017target 2021
Onshore wind project G0559, Benton County
Onshore wind
250 MWIn study Benton, WAWest Mar 2017target 2019
Onshore wind project GEN-2017-134, Oklahoma County
Onshore wind
250 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Onshore wind project GEN-2017-201, Wayne County
Onshore wind
250 MWAgreement signed Wayne, NESPP Nov 2017target 2028
Solar project J800, White County
Solar
250 MWUnder construction White, ILMISO Jun 20172024
EC500W Project
Onshore wind
247 MWAgreement signed Chaves, NMWest Jul 2017target 2020
Solar project GEN-2017-141, Wagoner County
Solar
242 MWAgreement signed Wagoner, OKSPP Nov 2017target 2027
Lutum Wind
Onshore wind ยท RWE
242 MWIn study Clay, TXERCOT Sep 2017target 2027
Giddings Wind
Onshore wind ยท Pioneer Natural Resources
240 MWIn study Upton, TXERCOT Sep 2017target 2030
Solar + storage project Company HQ, Pershing County
Solar + storage
240 MWPaused / redesign Pershing, NVWest Sep 2017target 2024
Sycamore Cross Solar
Solar
240 MWAgreement signed Isle Of Wight, VAPJM Mar 2017target 2026
Gas project IA-PNM-2017-14, San Juan County
Gas
236 MWAgreement signed San Juan, NMWest Oct 2017target 2022
Monte Cristo 1 Wind
Onshore wind ยท Terra-Gen
235 MWAgreement signed Hidalgo, TXERCOT Apr 2017target 2025
Monte Cristo II Wind
Onshore wind ยท Monte Cristo Windpower II, LLC
234 MWAgreement signed Hidalgo, TXERCOT Apr 2017target 2028
Onshore wind project GI-61, Nodaway County
Onshore wind
230 MWAgreement signed Nodaway, MOSoutheast May 2017target 2019
Heartland 2
Solar + storage
228 MWAgreement signed Fresno, CACAISO May 2017target 2028
Heartland 1
Solar + storage
228 MWAgreement signed Fresno, CACAISO May 2017target 2028
Baldy Mesa
Solar + storage
225 MWAgreement signed San Bernardino, CACAISO May 2017target 2026
Onshore wind project GEN-2017-233, Grady County
Onshore wind
215 MWAgreement signed Grady, OKSPP Nov 2017target 2027
South Branch Solar
Solar
205 MWPaused / redesign Hancock, OHPJM Aug 2017target 2025
Aramis Power Plant
Solar + storage
203 MWAgreement signed Alameda, CACAISO May 2017target 2026
Las Camas 1
Solar + storage
203 MWAgreement signed Merced, CACAISO May 2017target 2027
Onshore wind project GEN-2017-004, Cloud County
Onshore wind
202 MWAgreement signed Cloud, KSSPP Apr 2017target 2027
Solar project GEN-2017-226, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Battery storage project GEN-2017-227, Sedgwick County
Battery storage
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Solar project GEN-2017-220, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2026
Anson Solar 2
Solar + storage ยท Anson Solar Center 2, LLC
201 MWAgreement signed Jones, TXERCOT Jun 2017target 2026
Solar project GEN-2017-040, Ochiltree County
Solar
200 MWAgreement signed Ochiltree, TXSPP May 2017target 2026
Solar project GEN-2017-075, Johnston County
Solar
200 MWAgreement signed Johnston, OKSPP May 2017target 2026
Onshore wind project GEN-2017-121, Sumner County
Onshore wind
200 MWAgreement signed Sumner, KSSPP Nov 2017target 2026
Trade Post Solar Energy Center
Solar
200 MWAgreement signed Sullivan, INPJM Mar 2017target 2026
Battery storage project 17-067, Multnomah County
Battery storage
200 MWAgreement signed Multnomah, ORWest Sep 2017target 2031
Solar project J934, Crittenden County
Solar
200 MWUnder construction Crittenden, ARMISO Jun 20172024
Onshore wind project J722, Codington County
Onshore wind
200 MWUnder construction Codington, SDMISO Jun 2017target 2023
Rodeo Solar
Solar ยท Core Solar SPV I, LLC
200 MWAgreement signed Andrews, TXERCOT Jun 2017target 2026
Onshore wind project GEN-2017-144, Holt County
Onshore wind
200 MWAgreement signed Holt, NESPP Nov 2017target 2028
Anson Solar Center, Phase III
Solar ยท Anson Solar Center 3, LLC
200 MWIn study Jones, TXERCOT Jun 2017target 2027
Onshore wind project GEN-2017-133, Oklahoma County
Onshore wind
200 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Onshore wind project J866, Tunica County
Onshore wind
200 MWUnder construction Tunica, MSMISO Jun 20172024
Solar project GEN-2017-092, Muskogee County
Solar
200 MWAgreement signed Muskogee, OKSPP May 2017target 2026
Oakhurst Solar Farm
Solar + storage
200 MWIn study Mitchell, GASoutheast Apr 20172021
Solar project J878, Kenosha County
Solar
200 MWUnder construction Kenosha, WIMISO Jun 20172024
Solar project J805, Shelby County
Solar
199 MWUnder construction Shelby, INMISO Jun 2017target 2022
Gas project 54, Grays Harbor County
Gas
199 MWPaused / redesign Grays Harbor, WAWest Dec 2017target 2026
Sandrini Sol 1
Solar + storage
192 MWAgreement signed Kern, CACAISO May 2017target 2025
Redux Solar
Solar + storage
190 MWAgreement signed Fresno, CACAISO May 2017target 2026
Solar project J799, Washtenaw County
Solar
189 MWUnder construction Washtenaw, MIMISO Jun 2017target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)