🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Washington

ONSHORE WIND · WEST

Onshore wind project G0559, Benton County

Onshore wind project G0559, Benton County is a 250 MW onshore wind request in interconnection study in the West interconnection queue, in Benton County, Washington.

Queue statusIn planning
  1. PlanningQueued Mar 2017 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2019 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0559
Grid region
West (non-ISO utilities)
Connection point (POI)
BPA's McNary-Franklin 230 kV
Location
Benton County, Washington
Technology
Wind: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Study phase
Facility Study
Queue status
Active
Entered queue
1 March 2017
Proposed online date
December 2019

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem