🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Georgia

SOLAR + STORAGE · SOUTHEAST

Oakhurst Solar Farm

Oakhurst Solar Farm is a 200 MW solar + storage request in interconnection study in the Southeast interconnection queue, in Mitchell County, Georgia, connecting to Georgia Transmission.

Queue statusIn planning
  1. PlanningQueued Apr 2017 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingMay 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-100
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Raccoon Creek 230kV Sub
Location
Mitchell County, Georgia
Technology
Solar: 200 MW · Battery
Total requested
200 MW
Study phase
Facilities Study
Queue status
Active
Entered queue
19 April 2017
Proposed online date
December 2021
Came online
May 2021

Location

Marker shows the centre of Mitchell County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Mitchell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem