Hickory Part Solar & Battery

Hickory Part Solar & Battery is a 196 MW solar + storage request built and operating in the Southeast interconnection queue, in Mitchell County, Georgia, connecting to Southern Company.

Queue statusOperating
  1. Planning (completed)
  2. ConsentedJun 2020 (completed)
  3. Construction (completed)
  4. OperatingJun 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
IC-805
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Location
Mitchell County, Georgia
Technology
Solar: 196 MW · Battery
Total requested
196 MW
Study phase
Operational
Queue status
Operational
Agreement signed
19 June 2020
Came online
June 2022

Location

Marker shows the centre of Mitchell County; the queue data does not give exact sites.