SOLAR Β· SOUTHEASTTurkey Run Solar
Turkey Run Solar is a 196 MW solar request built and operating in the Southeast interconnection queue, connecting to Southern Company.
Request details
- Queue ID
- IC-589
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Technology
- Solar: 196 MW
- Total requested
- 196 MW
- Study phase
- Operational
- Queue status
- Operational
- Came online
- June 2022
Location
Marker shows the centre of County; the queue data does not give exact sites.
Other requests in County
- Solar project IC-774, Mitchell CountySolar Β· 260 MW Β· agreement signed
- Solar + storage project IC-1276, Mitchell CountySolar + storage Β· 150 MW Β· agreement signed
- Flint River 780 MW UnitGas Β· 780 MW Β· in study
- Flint River 2 780 MW UnitGas Β· 780 MW Β· in study
- Pecan Energy StorageSolar + storage Β· 208 MW Β· in study
- Oakhurst Solar FarmSolar + storage Β· 200 MW Β· in study
- Solar project IC-1149, Mitchell CountySolar Β· 250 MW Β· suspended
- Solar project IC-1015, Mitchell CountySolar Β· 150 MW Β· suspended
- BacontonGas Β· 500 MW Β· built
- Hickory Part Solar & BatterySolar + storage Β· 196 MW Β· built
- Southern Oak Solar Energy Center Phase IISolar Β· 160 MW Β· built
- SowegaGas Β· 100 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem