United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Aramis Power Plant

Aramis Power Plant is a 203 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Alameda County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued May 2017 (completed)
  2. ConsentedNov 2019 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1349
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Cayetano 230 kV
Location
Alameda County, California
Technology
Solar: 101 MW · Battery: 101 MW
Total requested
203 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
1 May 2017
Agreement signed
26 November 2019
Proposed online date
July 2026

Location

Marker shows the centre of Alameda County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Alameda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem