🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Emerita Energy Storage

Emerita Energy Storage is a 206 MW battery storage request in interconnection study in the CAISO interconnection queue, in Alameda County, California, connecting to PGAE.

Queue statusIn planning
  1. PlanningQueued Apr 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
2221
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
TESLA 230 kV
Location
Alameda County, California
Technology
Battery: 206 MW
Total requested
206 MW
Service type
Network resource (NRIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Active
Entered queue
17 April 2023
Proposed online date
March 2028

Location

Marker shows the centre of Alameda County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Alameda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem