United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA (2023 requests) — page 16
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project GEN-2023-SR20, Custer County Battery storage |
120 MW | In study |
| Battery storage project GEN-2023-SR12, Cochran County Battery storage |
120 MW | Agreement signed |
| Battery storage project 899053, Wilkes County Battery storage |
120 MW | Agreement signed |
| Battery storage project AI2-231, Prince William County Battery storage |
120 MW | In study |
| Solar + storage project J2152, Tangipahoa Parish County Solar + storage |
120 MW | In study |
| Surplus; J442 Other |
120 MW | In study |
| Solar + storage project GEN-2023-153, Perkins County Solar + storage |
120 MW | In study |
| Pelham Solar Solar |
120 MW | In study |
| Surplus; G736 Other |
120 MW | In study |
| Onshore wind project GEN-2023-088, Okfuskee County Onshore wind |
117 MW | In study |
| Butcherbird Solar Solar · Butcherbird Solar, LLC |
116 MW | In study |
| Pioneer Hutt Solar (Alternative POI) Solar · NextEra Energy Interconnection Holdings LLC |
116 MW | In study |
| SR Bacon II Solar Solar |
115 MW | In study |
| Solar project GEN-2022-104, Bryan County Solar |
113 MW | In study |
| Megacharge BESS Battery storage · SMT Harlingen III LLC |
110 MW | In study |
| Solheim Solar Solar · Solheim Solar, LLC |
109 MW | In study |
| Vault Solar Solar · PPM THR Solar |
109 MW | In study |
| Toland Renewable Energy Park Onshore wind |
108 MW | In study |
| SR Norwood Solar Solar |
107 MW | Under construction |
| Santa Monica Solar Solar · Karol Solar IV |
106 MW | In study |
| Waterloo BESS 1 Solar + storage · Waterloo Solar, LLC |
106 MW | Agreement signed |
| Voyager Energy Storage Battery storage |
105 MW | In study |
| Solar project IC-1136, Lincoln County Solar |
105 MW | Paused / redesign |
| Ulua Battery storage |
105 MW | In study |
| Happy Dog Storage Solar + storage · Rosula Solar LLC |
105 MW | Agreement signed |
| Stargazer BESS Solar + storage · Stargazer Solar LLC |
105 MW | In study |
| Neutron Storage Battery storage · Elawan Neutron Storage, LLC |
105 MW | Agreement signed |
| Cadet Storage Battery storage · TX BESS 5, LLC |
104 MW | In study |
| Gas project Company 258, Clark County Gas |
104 MW | Paused / redesign |
| Nelson Solar |
104 MW | In study |
| Tioga Pass Battery storage |
103 MW | In study |
| Evans Creek Energy Storage Battery storage · Evans Creek Energy Storage LLC |
103 MW | In study |
| Black Bear Solar Solar + storage · ESCONDIDO DRAW RESOURCES, LLC |
103 MW | In study |
| Bonita Bateria Battery storage |
103 MW | In study |
| Firebird BESS Battery storage · TX BESS 6, LLC |
103 MW | In study |
| Millennium Energy Storage Battery storage |
103 MW | Paused / redesign |
| Roost Energy Storage Battery storage · Bluff Creek Energy Storage LLC |
102 MW | In study |
| Big Five Storage Battery storage · TX BESS 3 LLC |
102 MW | In study |
| Cassia Battery storage |
102 MW | In study |
| Droga Battery storage |
102 MW | In study |
| Stoneridge BESS Battery storage · Stoneridge Solar, LLC |
102 MW | Agreement signed |
| Myers Solar Solar + storage · BT Myers Solar, LLC |
102 MW | In study |
| Battery storage project GEN-2023-SR27, Mayes County Battery storage |
102 MW | In study |
| Pinnacle Point Energy Storage Battery storage · GCI Pinnacle Point, LLC |
101 MW | In study |
| Blue Creek Energy Storage Battery storage · Blue Creek Energy Storage, LLC |
101 MW | In study |
| Kinney County Energy Battery storage · Kinney County Energy, LLC |
101 MW | In study |
| Lyford Energy Battery storage · Lyford Energy, LLC |
101 MW | In study |
| Southside Energy Battery storage · Southside Energy, LLC |
101 MW | In study |
| Hadrian Energy Storage Battery storage · Hadrian Energy Storage, LLC |
101 MW | In study |
| Hynes Bay Energy Storage Battery storage · Hynes Bay Energy Storage, LLC |
101 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)309 · 110.9 GW
- ERCOT (Texas)356 · 76.0 GW
- CAISO (California)107 · 53.4 GW
- Southeast (non-ISO utilities)210 · 24.0 GW
- SPP (Southwest Power Pool)82 · 15.1 GW
- PJM (Mid-Atlantic, Midwest)156 · 14.6 GW
- MISO (Midcontinent)23 · 3,679 MW
- ISO-NE (New England)6 · 1,053 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)