United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · SPP

Battery storage project GEN-2023-SR12, Cochran County

Battery storage project GEN-2023-SR12, Cochran County is a 120 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Cochran County, Texas, connecting to Xcel.

Queue statusConsented
  1. PlanningQueued Feb 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingSep 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2023-SR12
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
Xcel
Connection point (POI)
Tap Cochran to Lehman 115 kV Line
Location
Cochran County, Texas
Technology
Battery: 120 MW
Total requested
120 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
13 February 2023
Proposed online date
September 2025
Came online
September 2025

Location

Marker shows the centre of Cochran County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Cochran County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem