United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· SPPSolar project GEN-2022-227, Cochran County
Solar project GEN-2022-227, Cochran County is a 244 MW solar request withdrawn in the SPP interconnection queue, in Cochran County, Texas, connecting to SPS.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2023 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-227
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Tolk βΓΓ¬ Yoakum 230 kV line
- Location
- Cochran County, Texas
- Technology
- Solar: 244 MW
- Total requested
- 244 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 28 February 2023
- Proposed online date
- September 2028
- Withdrawn
- November 2023
Location
Marker shows the centre of Cochran County; the queue data does not give exact sites.
Other requests in Cochran County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem