United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· SPP

Solar project GEN-2022-227, Cochran County

Solar project GEN-2022-227, Cochran County is a 244 MW solar request withdrawn in the SPP interconnection queue, in Cochran County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-227
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tolk β€šΓ„Γ¬ Yoakum 230 kV line
Location
Cochran County, Texas
Technology
Solar: 244 MW
Total requested
244 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
28 February 2023
Proposed online date
September 2028
Withdrawn
November 2023

Location

Marker shows the centre of Cochran County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Cochran County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem