🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Stargazer BESS

Stargazer BESS is a 105 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0556
Grid region
ERCOT (Texas)
Developer
Stargazer Solar LLC
Connection point (POI)
44010 WA Parish - 42980 Nash 138 kV
Location
Brazoria County, Texas
Technology
Battery: 105 MW · Battery
Total requested
105 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
30 October 2023
Proposed online date
February 2027

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brazoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem