🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Millennium Energy Storage

Millennium Energy Storage is a 103 MW battery storage request suspended in the ERCOT interconnection queue, in Martin County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued May 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0431
Grid region
ERCOT (Texas)
Location
Martin County, Texas
Technology
Battery: 103 MW
Total requested
103 MW
Queue status
Suspended
Entered queue
2 May 2023

Location

Marker shows the centre of Martin County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Martin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem