Picadillo BESS

Picadillo BESS is a 101 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Martin County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2022 (completed)
  2. ConsentedJan 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0275
Grid region
ERCOT (Texas)
Developer
Black Mountain Energy Storage II
Connection point (POI)
23837 Buffalo 138kV
Location
Martin County, Texas
Technology
Battery: 101 MW
Total requested
101 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
7 March 2022
Agreement signed
23 January 2024
Proposed online date
May 2028

Location

Marker shows the centre of Martin County; the queue data does not give exact sites.