United States › Grid › Interconnection queues › Georgia

SOLAR · SOUTHEAST

Solar project IC-1136, Lincoln County

Solar project IC-1136, Lincoln County is a 105 MW solar request suspended in the Southeast interconnection queue, in Lincoln County, Georgia, connecting to Southern Company.

Queue statusPaused / redesign
  1. PlanningQueued Apr 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IC-1136
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Anthony Shoals - Washington 115 kV Line
Location
Lincoln County, Georgia
Technology
Solar: 105 MW
Total requested
105 MW
Service type
Network resource (NRIS)
Queue status
Suspended
Entered queue
14 April 2023
Proposed online date
September 2027

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem