United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTVault Solar
Vault Solar is a 109 MW solar request in interconnection study in the ERCOT interconnection queue, in Palo Pinto County, Texas.
Queue statusIn planning
- PlanningQueued Jun 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0482
- Grid region
- ERCOT (Texas)
- Developer
- PPM THR Solar
- Connection point (POI)
- Tap #331 Rwmiller - #320 Jaybird 138kV
- Location
- Palo Pinto County, Texas
- Technology
- Solar: 109 MW
- Total requested
- 109 MW
- Study phase
- SS Completed, FIS Completed, No IA
- Queue status
- Active
- Entered queue
- 28 June 2023
- Proposed online date
- December 2026
Location
Marker shows the centre of Palo Pinto County; the queue data does not give exact sites.
Other requests in Palo Pinto County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem