Interconnection queue in the USA (2025 requests) — page 14

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,836452.0 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,836 requests · page 14 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Cricket Storage
Battery storage · Cricket Storage, LLC
232 MWIn study Henderson, TXERCOT Apr 2025target 2028
Onshore wind project J4068, Marshall County
Onshore wind
232 MWIn study Marshall, IAMISO Oct 2025target 2030
Allthorn Solar
Solar + storage · ALLTHORN SOLAR, LLC
232 MWIn study Duval, TXERCOT Feb 2025target 2029
Onshore wind project J2104, Murray County
Onshore wind
230 MWIn study Murray, MNMISO Sep 2025target 2024
Gas project 25-IC-1317, Autauga County
Gas
229 MWIn study Autauga, ALSoutheast Apr 2025target 2029
Gas project GEN-2024-206, Jackson County
Gas
226 MWIn study Jackson, MOSPP Mar 2025target 2026
Sim Gideon Gas Rice
Gas · LCRA
226 MWIn study Bastrop, TXERCOT Jul 2025target 2031
Solar project GEN-2024-374, Scotts Bluff County
Solar
225 MWIn study Scotts Bluff, NESPP Mar 2025target 2030
Solar project GEN-2024-311, Chaves County
Solar
225 MWIn study Chaves, NMSPP Mar 2025target 2030
Battery storage project GEN-2024-326, Stark County
Battery storage
225 MWIn study Stark, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-330, Butler County
Battery storage
225 MWIn study Butler, KSSPP Mar 2025target 2028
Battery storage project T2-061, Salt Lake County
Battery storage
225 MWIn study Salt Lake, UTWest Sep 2025target 2027
Onshore wind project GEN-2024-216, Custer County
Onshore wind
225 MWIn study Custer, MTSPP Mar 2025target 2027
Solar + storage project IA-PNM-2025-05, Bernalillo County
Solar + storage
225 MWIn study Bernalillo, NMWest Mar 2025target 2030
Solar project J4151, Redwood County
Solar
225 MWIn study Redwood, MNMISO Oct 2025target 2030
Onshore wind project GI-CS-2025-24, Kit Carson County
Onshore wind
225 MWIn study Kit Carson, COWest Sep 2025target 2029
Tolivar Power Plant Phase 2
Gas · Pecos Power Plant, LLC
225 MWIn study Reeves, TXERCOT Jul 2025target 2027
Grayback Solar
Solar · Grayback Solar, LLC
222 MWIn study Wilbarger, TXERCOT Nov 2025target 2028
Miracle Ranch Solar SLF
Solar + storage · Miracle Ranch LLC
222 MWIn study Webb, TXERCOT Feb 2025target 2028
Solar project J4051, Jefferson Davis Parish County
Solar
220 MWIn study Jefferson Davis Parish, LAMISO Sep 2025target 2030
Solar project AH1-055, Jackson County
Solar · Furnace Solar, LLC
220 MWIn study Jackson, OHPJM Feb 2025target 2026
Battery storage project GEN-2025-SR8, Noble County
Battery storage
220 MWIn study Noble, OKSPP May 2025target 2027
Onshore wind project GEN-2024-346, Nowata County
Onshore wind
220 MWIn study Nowata, OKSPP Mar 2025target 2030
Solar project GEN-2024-257, Pratt County
Solar
220 MWIn study Pratt, KSSPP Mar 2025target 2029
Solar project J4050, Jefferson Davis Parish County
Solar
220 MWIn study Jefferson Davis Parish, LAMISO Sep 2025target 2030
Solar project J4041, Menard County
Solar
220 MWIn study Menard, ILMISO Jun 2025target 2030
Gas project ERAS-2025-002, Hale County
Gas
217 MWIn study Hale, TXSPP Sep 2025target 2027
Diamond Sage Solar 1
Solar + storage · DGC Renewables, LLC
214 MWIn study Webb, TXERCOT Jan 2025target 2028
Diamond Sage Solar 2
Solar + storage · DGC Renewables, LLC
214 MWIn study Webb, TXERCOT Jan 2025target 2028
Solar project J3940, Isabella County
Solar
214 MWIn study Isabella, MIMISO Feb 2025target 2030
Sandhill Energy Storage
Battery storage · Xcel Energy
214 MWIn study Olmsted, MNMISO Aug 2025target 2025
Deckerville Solar Park Project
Solar · DTE Electric
213 MWIn study Sanilac, MIMISO Aug 2025target 2028
Mesquite Creek Windpower Repower
Onshore wind · Mesquite Creek Wind LLC
213 MWIn study Dawson, TXERCOT Apr 2025target 2027
Gypsum Plains Storage
Solar + storage · Gypsum Plains Solar, LLC
211 MWIn study Ector, TXERCOT Jan 2025target 2029
Solar project AG2-245, Starke County
Solar · STARKE CENTRAL PROJECT, LLC
210 MWIn study Starke, INPJM Mar 2025target 2023
Solar project AG2-184, Knott County
Solar · STMO bn, LLC
210 MWIn study Knott, KYPJM Feb 2025target 2024
Treehouse Storage
Solar + storage · Treehouse Solar, LLC
209 MWIn study Grimes, TXERCOT Jul 2025target 2028
Battery storage project GEN-2025-SR30, Dewey County
Battery storage
209 MWIn study Dewey, OKSPP Aug 2025target 2027
Battery storage project MPC04600, Eddy County
Battery storage
209 MWIn study Eddy, NDMISO Nov 2025target 2028
Amite Energy Storage II
Battery storage · NextEra Energy Resources Development, LLC
208 MWIn study Tangipahoa Parish, LAMISO Aug 2025target 2028
Gulf Prairie BESS
Solar + storage · Gulf Prairie Energy LLC
208 MWIn study Brazoria, TXERCOT Sep 2025target 2028
Gas project 303, Colleton County
Gas
208 MWIn study Colleton, SCSoutheast May 2025target 2032
Gas project 302, Colleton County
Gas
208 MWIn study Colleton, SCSoutheast May 2025target 2032
Metro BESS
Battery storage · Metro BESS LLC
207 MWIn study Caldwell, TXERCOT Feb 2025target 2030
Oak Belt Storage
Solar + storage · Oak Belt Storage, LLC
207 MWIn study Victoria, TXERCOT Dec 2025target 2029
Zunkerville BESS
Solar + storage · Zunkerville Energy, LLC
207 MWIn study Karnes, TXERCOT Sep 2025target 2028
Wolfram Storage
Battery storage · Nova Clean Energy, LLC
207 MWIn study Calhoun, TXERCOT May 2025target 2027
Champion Road BESS
Battery storage · Horizon Energy Storage Greenfield Project Holdings LLC
206 MWIn study Angelina, TXERCOT Feb 2025target 2028
Maximino Road BESS
Battery storage · Horizon Energy Storage Greenfield Project Holdings LLC
206 MWIn study Comal, TXERCOT Mar 2025target 2028
Roan Solar Phase 1
Solar · Roan Solar, LLC
206 MWIn study Sterling, TXERCOT Oct 2025target 2029
Page 14 of 37

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)