United States › Grid › Interconnection queues › Oklahoma
BATTERY STORAGE · SPPBattery storage project GEN-2025-SR8, Noble County
Battery storage project GEN-2025-SR8, Noble County is a 220 MW battery storage request in interconnection study in the SPP interconnection queue, in Noble County, Oklahoma, connecting to OG&E.
Queue statusIn planning
- PlanningQueued May 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2025-SR8
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OG&E
- Connection point (POI)
- White Tail 345kV Substation
- Location
- Noble County, Oklahoma
- Technology
- Battery: 220 MW
- Total requested
- 220 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA PENDING
- Queue status
- Active
- Entered queue
- 30 May 2025
- Proposed online date
- January 2027
Location
Marker shows the centre of Noble County; the queue data does not give exact sites.
Other requests in Noble County
- Solar project GEN-2021-018, Noble CountySolar · 231 MW · agreement signed
- Battery storage project GEN-2021-019, Noble CountyBattery storage · 74.9 MW · agreement signed
- Solar project GEN-2024-056, Noble CountySolar · 120 MW · in study
- Battery storage project GEN-2025-SR12, Noble CountyBattery storage · 116 MW · in study
- Battery storage project GEN-2025-SR11, Noble CountyBattery storage · 112 MW · in study
- Onshore wind project GEN-2015-047, Noble CountyOnshore wind · 300 MW · built
- Coal project GEN-2006-037, Noble CountyCoal · 900 MW · withdrawn
- Onshore wind project GEN-2021-071, Noble CountyOnshore wind · 403 MW · withdrawn
- Onshore wind project GEN-2008-111, Noble CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project GEN-2015-030, Noble CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2016-101, Noble CountyOnshore wind · 195 MW · withdrawn
- Solar project GEN-2015-067, Noble CountySolar · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem