ONSHORE WIND Β· SPP

Onshore wind project GEN-2015-030, Noble County

Onshore wind project GEN-2015-030, Noble County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Noble County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2015 (completed)
  2. Withdrawn / abandonedMar 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingNov 2017 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2015-030
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Sooner 345kV
Location
Noble County, Oklahoma
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
TERMINATED
Queue status
Withdrawn
Entered queue
19 March 2015
Proposed online date
November 2017
Came online
November 2017
Withdrawn
March 2018

Location

Marker shows the centre of Noble County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Noble County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem