Solar project GEN-2015-067, Noble County

Solar project GEN-2015-067, Noble County is a 150 MW solar request withdrawn in the SPP interconnection queue, in Noble County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2015 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2015-067
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Sooner 138 kV Substation
Location
Noble County, Oklahoma
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
7 October 2015
Proposed online date
October 2017
Withdrawn
June 2017

Location

Marker shows the centre of Noble County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Noble County