United States › Grid › Interconnection queues › North Dakota
BATTERY STORAGE · SPPBattery storage project GEN-2024-326, Stark County
Battery storage project GEN-2024-326, Stark County is a 225 MW battery storage request in interconnection study in the SPP interconnection queue, in Stark County, North Dakota, connecting to WAPA.
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-326
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Belfield 230 kV Substation
- Location
- Stark County, North Dakota
- Technology
- Battery: 225 MW
- Total requested
- 225 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- January 2028
Location
Marker shows the centre of Stark County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Stark County
- Onshore wind project GI-1502, Stark CountyOnshore wind · 182 MW · in study
- Onshore wind project GI-1509, Stark CountyOnshore wind · 150 MW · in study
- Battery storage project GEN-2024-359, Stark CountyBattery storage · 100 MW · in study
- Onshore wind project GI-1414, Stark CountyOnshore wind · 150 MW · built
- Coal project GI-0217, Stark CountyCoal · 500 MW · withdrawn
- Onshore wind project J050, Stark CountyOnshore wind · 250 MW · withdrawn
- Solar project GEN-2023-198, Stark CountySolar · 250 MW · withdrawn
- Solar project GEN-2022-220, Stark CountySolar · 250 MW · withdrawn
- Onshore wind project GI-1312, Stark CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project GI-1415, Stark CountyOnshore wind · 150 MW · withdrawn
- Onshore wind project GEN-2015-091, Stark CountyOnshore wind · 101 MW · withdrawn
- Onshore wind project GEN-2016-066, Stark CountyOnshore wind · 13.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem