ONSHORE WIND Β· MISO

Onshore wind project J050, Stark County

Onshore wind project J050, Stark County is a 250 MW onshore wind request withdrawn in the MISO interconnection queue, in Stark County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2009 (completed)
  2. Withdrawn / abandonedJan 2010 (project stopped here)
  3. ConsentedJan 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J050
Grid region
MISO (Midcontinent)
Connection point (POI)
MDU Dickinson - Beulah 115 kV
Location
Stark County, North Dakota
Technology
Wind: 250 MW
Total requested
250 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
29 June 2009
Agreement signed
13 January 2010
Proposed online date
June 2012
Withdrawn
January 2010

Location

Marker shows the centre of Stark County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Stark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem