United States › Grid › Interconnection queues › Kansas
SOLAR · SPPSolar project GEN-2024-257, Pratt County
Solar project GEN-2024-257, Pratt County is a 220 MW solar request in interconnection study in the SPP interconnection queue, in Pratt County, Kansas, connecting to SUNC.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-257
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Skellyville 115 kV Tap Substation
- Location
- Pratt County, Kansas
- Technology
- Solar: 220 MW
- Total requested
- 220 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- October 2029
Location
Marker shows the centre of Pratt County; the queue data does not give exact sites.
Other requests in Pratt County
- Onshore wind project GEN-2019-001, Pratt CountyOnshore wind · 25.0 MW · agreement signed
- Solar + storage project GEN-2024-272, Pratt CountySolar + storage · 199 MW · in study
- Onshore wind project GEN-2015-025, Pratt CountyOnshore wind · 220 MW · built
- Onshore wind project GEN-2015-024, Pratt CountyOnshore wind · 220 MW · built
- Onshore wind project GEN-2015-090, Pratt CountyOnshore wind · 220 MW · built
- Battery storage project GEN-2023-215, Pratt CountyBattery storage · 225 MW · withdrawn
- Onshore wind project GEN-2014-049, Pratt CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2023-118, Pratt CountyOnshore wind · 200 MW · withdrawn
- Solar project GEN-2023-111, Pratt CountySolar · 200 MW · withdrawn
- Onshore wind project GEN-2009-003, Pratt CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2006-022, Pratt CountyOnshore wind · 150 MW · withdrawn
- Solar project GEN-2023-112, Pratt CountySolar · 130 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem