🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kansas

SOLAR + STORAGE · SPP

Solar + storage project GEN-2024-272, Pratt County

Solar + storage project GEN-2024-272, Pratt County is a 199 MW solar + storage request in interconnection study in the SPP interconnection queue, in Pratt County, Kansas, connecting to SUNC.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-272
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Sawyer 115 kV Substation
Location
Pratt County, Kansas
Technology
Solar: 199 MW · Battery
Total requested
199 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
December 2029

Location

Marker shows the centre of Pratt County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Pratt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem