United States › Grid › Interconnection queues › Kansas

ONSHORE WIND · SPP

Onshore wind project GEN-2015-025, Pratt County

Onshore wind project GEN-2015-025, Pratt County is a 220 MW onshore wind request built and operating in the SPP interconnection queue, in Pratt County, Kansas, connecting to WERE.

Queue statusOperating
  1. PlanningQueued Mar 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2015-025
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Tap Thistle – Wichita 345kV Dbl CKT
Location
Pratt County, Kansas
Technology
Wind: 220 MW
Total requested
220 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
26 March 2015
Proposed online date
December 2016
Came online
December 2016

Location

Marker shows the centre of Pratt County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Pratt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem