πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

SOLAR Β· SPP

Solar project GEN-2023-111, Pratt County

Solar project GEN-2023-111, Pratt County is a 200 MW solar request withdrawn in the SPP interconnection queue, in Pratt County, Kansas, connecting to Evergy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandonedMar 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-111
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
Evergy
Connection point (POI)
Buffalo Flats 345 kV Substation
Location
Pratt County, Kansas
Technology
Solar: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
2 October 2023
Proposed online date
December 2030
Withdrawn
March 2024

Location

Marker shows the centre of Pratt County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Pratt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem