United States › Grid › Interconnection queues › Louisiana
BATTERY STORAGE · MISOAmite Energy Storage II
Amite Energy Storage II is a 208 MW battery storage request in interconnection study in the MISO interconnection queue, in Tangipahoa Parish County, Louisiana, connecting to DEMCO.
Queue statusIn planning
- PlanningQueued Aug 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- E0024
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DEMCO
- Developer
- NextEra Energy Resources Development, LLC
- Connection point (POI)
- Amite 115kV Substation
- Location
- Tangipahoa Parish County, Louisiana
- Technology
- Battery: 208 MW
- Total requested
- 208 MW
- Service type
- Network resource (NRIS)
- Study phase
- Request Status: Active; Post GIA Status: Not started
- Queue status
- Active
- Entered queue
- 6 August 2025
- Proposed online date
- February 2028
Location
Marker shows the centre of Tangipahoa Parish County; the queue data does not give exact sites.
Other requests in Tangipahoa Parish County
- Solar project J909, Tangipahoa Parish CountySolar · 100 MW · under construction
- Solar project J1219, Tangipahoa Parish CountySolar · 100 MW · under construction
- Battery storage project J1257, Tangipahoa Parish CountyBattery storage · 20.0 MW · under construction
- Solar project J1870, Tangipahoa Parish CountySolar · 200 MW · in study
- Solar + storage project J2152, Tangipahoa Parish CountySolar + storage · 120 MW · in study
- Surplus; J909Other · 100 MW · in study
- Solar project J3365, Tangipahoa Parish CountySolar · 100 MW · withdrawn
- Battery storage project J1871, Tangipahoa Parish CountyBattery storage · 60.0 MW · withdrawn
- Battery storage project J2013, Tangipahoa Parish CountyBattery storage · 52.9 MW · withdrawn
- Solar project J1985, Tangipahoa Parish CountySolar · 50.0 MW · withdrawn
- Battery storage project J2012, Tangipahoa Parish CountyBattery storage · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem