United States › Grid › Interconnection queues › Utah
BATTERY STORAGE · WESTBattery storage project T2-061, Salt Lake County
Battery storage project T2-061, Salt Lake County is a 225 MW battery storage request in interconnection study in the West interconnection queue, in Salt Lake County, Utah, connecting to PacifiCorp.
Queue statusIn planning
- PlanningQueued Sep 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- T2-061
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Copper Hills substation
- Location
- Salt Lake County, Utah
- Technology
- Battery: 225 MW
- Total requested
- 225 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 12 September 2025
- Proposed online date
- December 2027
Location
Marker shows the centre of Salt Lake County; the queue data does not give exact sites.
Other requests in Salt Lake County
- Battery storage project C2-10, Salt Lake CountyBattery storage · 500 MW · agreement signed
- Battery storage project C2-28, Salt Lake CountyBattery storage · 199 MW · agreement signed
- Battery storage project PIS087, Salt Lake CountyBattery storage · 500 MW · in study
- Battery storage project T2-084, Salt Lake CountyBattery storage · 500 MW · in study
- Battery storage project PIS088, Salt Lake CountyBattery storage · 199 MW · in study
- Battery storage project T2-080, Salt Lake CountyBattery storage · 160 MW · in study
- Gas project PIS091, Salt Lake CountyGas · 17.0 MW · in study
- Gas project T2-015, Salt Lake CountyGas · 7.0 MW · in study
- Wind + storage project C1-04, Salt Lake CountyWind + storage · 6.0 MW · in study
- Onshore wind project C1-58, Salt Lake CountyOnshore wind · 2.0 MW · in study
- Battery storage project TCS-48, Salt Lake CountyBattery storage · 200 MW · built
- Gas project 3, Salt Lake CountyGas · 200 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem