United States › Grid › Interconnection queues › Utah

BATTERY STORAGE · WEST

Battery storage project C2-28, Salt Lake County

Battery storage project C2-28, Salt Lake County is a 199 MW battery storage request with a signed interconnection agreement in the West interconnection queue, in Salt Lake County, Utah, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued Apr 2022 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2031 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
C2-28
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Dominguez Grid, LLC
Connection point (POI)
Terminal substation
Location
Salt Lake County, Utah
Technology
Battery: 199 MW
Total requested
199 MW
Service type
Network resource (NRIS)
Study phase
LGIA executed 10/2/2024
Queue status
Active
Entered queue
18 April 2022
Proposed online date
February 2031

Location

Marker shows the centre of Salt Lake County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Salt Lake County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem