OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in PJM (Mid-Atlantic, Midwest) — page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,248140.4 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,248 requests · page 11 of 25
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AJ1-020, Caroline County
Solar
86.4 MWIn study Caroline, VAPJM Jun 2023target 2029
Solar project AG2-369, Greensville County
Solar · Virginia Electric and Power Company
86.0 MWIn study Greensville, VAPJM Feb 2025target 2025
Waller Solar I
Solar
86.0 MWAgreement signed Lancaster, VAPJM Mar 2018target 2027
Harvey Solar I
Solar
85.0 MWAgreement signed Licking, OHPJM Jun 2020target 2029
ACE Development Company, LLC
Solar · ACE Development Company, LLC
85.0 MWIn study Cumberland, VAPJM Mar 2025target 2026
Solar project AH2-115, Tioga County
Solar
85.0 MWIn study Tioga, PAPJM Feb 2022target 2026
Solar project AH2-116, Cambria County
Solar
85.0 MWIn study Cambria, PAPJM Feb 2022target 2026
Solar project AH2-130
Solar
85.0 MWIn study KYPJM Feb 2022target 2026
Battery storage project AG2-339, Sussex County
Battery storage · Cassius Blue Solar LLC
85.0 MWIn study Sussex, VAPJM Apr 2025target 2024
Prairie Flyer Energy Storage
Battery storage
85.0 MWAgreement signed Montgomery, OHPJM Sep 2020target 2028
Solar + storage project AI1-112, Champaign County
Solar + storage
85.0 MWIn study Champaign, OHPJM Aug 2022target 2026
Battery storage project AH1-673, Cook County
Battery storage · Big Shoulders Storage LLC
85.0 MWIn study Cook, ILPJM Feb 2025
Solar + storage project AI1-165, Green County
Solar + storage
85.0 MWIn study Green, KYPJM Sep 2022target 2026
Murch Solar
Solar
85.0 MWAgreement signed Van Buren, MIPJM Aug 2019target 2027
Windsor PVI
Solar
85.0 MWPaused / redesign Isle Of Wight, VAPJM Mar 2017target 2023
Solar project AH2-164, Crawford County
Solar
85.0 MWIn study Crawford, OHPJM Mar 2022target 2026
Carnation
Solar
84.0 MWAgreement signed Fairfield, OHPJM Mar 2020target 2028
Solar project AI2-115, Delaware County
Solar
84.0 MWIn study Delaware, INPJM Feb 2023target 2026
Battery storage project AH2-374, Richland County
Battery storage
84.0 MWIn study Richland, OHPJM Mar 2022target 2027
MPG Solar
Solar
83.6 MWAgreement signed Centre, PAPJM Mar 2019target 2028
Solar project AI2-330, Madison County
Solar
83.5 MWIn study Madison, OHPJM Mar 2023target 2028
Onshore wind project AH2-247, Cambria County
Onshore wind
83.3 MWIn study Cambria, PAPJM Mar 2022target 2028
Onshore wind project AH2-248, Cambria County
Onshore wind
83.3 MWIn study Cambria, PAPJM Mar 2022target 2028
Onshore wind project AH2-403, Cambria County
Onshore wind
83.3 MWIn study Cambria, PAPJM Mar 2022target 2028
Battery storage project AH2-422, Westmoreland County
Battery storage
83.0 MWIn study Westmoreland, PAPJM Mar 2022target 2025
Solar + storage project AI1-132, Washington County
Solar + storage
83.0 MWIn study Washington, KYPJM Sep 2022target 2029
Hawthorn Solar
Solar
83.0 MWAgreement signed Delaware, INPJM Sep 2019target 2028
Solar project AI2-063, Mckean County
Solar
82.5 MWIn study Mckean, PAPJM Feb 2023target 2027
Stonecrop Solar
Solar · CPV Stonecrop Solar, LLC
82.0 MWAgreement signed Hardin, KYPJM Sep 2020target 2029
Beaver Creek Solar
Solar
80.3 MWPaused / redesign Franklin, PAPJM Feb 2018target 2024
Solar project AH1-239, Boone County
Solar · Clinton Solar, LLC
80.0 MWIn study Boone, KYPJM Mar 2025target 2024
Solar + storage project AI2-004, Brunswick County
Solar + storage
80.0 MWIn study Brunswick, VAPJM Oct 2022target 2026
Bright Mountain Solar
Solar
80.0 MWAgreement signed Perry, KYPJM Jul 2020target 2027
Solar project AG2-423, Barbour County
Solar · Falling Waters Solar, LLC
80.0 MWIn study Barbour, WVPJM Jan 2025target 2024
Wilson Solar
Solar
80.0 MWAgreement signed Erie, PAPJM Aug 2019target 2028
Poseidon Storage
Battery storage · Poseidon Energy, LLC
80.0 MWIn study Fayette, PAPJM Feb 2025target 2024
Battery storage project AH1-461, Tazewell County
Battery storage · Lakeside Energy, LLC
80.0 MWIn study Tazewell, VAPJM Feb 2025target 2024
Solar project AH2-165, Fulton County
Solar
80.0 MWIn study Fulton, OHPJM Mar 2022target 2025
Solar + storage project AI1-178, Campbell County
Solar + storage
80.0 MWIn study Campbell, VAPJM Sep 2022target 2027
Solar project AG2-213, Lunenburg County
Solar · Virginia Electric and Power Company
80.0 MWIn study Lunenburg, VAPJM Feb 2025target 2025
Frasier Solar
Solar
80.0 MWAgreement signed Knox, OHPJM Mar 2020target 2028
Seven Bridges Solar
Solar
80.0 MWPaused / redesign Mecklenburg, VAPJM Sep 2017target 2026
Battery storage project AG2-675, Rock Island County
Battery storage · Scout Solar DevCo LLC
80.0 MWIn study Rock Island, ILPJM Feb 2025target 2024
Solar project AG2-568
Solar · Sundial Energy, LLC
80.0 MWIn study WVPJM Feb 2025target 2024
Walker Solar Two
Solar
80.0 MWAgreement signed Juniata, PAPJM Mar 2020target 2026
Battery storage project AG2-518, Montgomery County
Battery storage · Delorean Power LLC dba Lightshift Energy
80.0 MWIn study Montgomery, VAPJM Feb 2025target 2024
Solar project AH1-666, Fleming County
Solar · Fleming Solar, LLC
80.0 MWIn study Fleming, KYPJM Mar 2025
Solar + storage project AG2-548, Jackson County
Solar + storage · Hamden Energy LLC
80.0 MWIn study Jackson, OHPJM Feb 2025target 2023
Halifax County Solar
Solar
80.0 MWAgreement signed Halifax, NCPJM Nov 2016target 2026
Solar project AH1-665, Fleming County
Solar · Hummingbird Energy LLC
80.0 MWIn study Fleming, KYPJM May 2025
Page 11 of 25

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)