BATTERY STORAGE · PJMBattery storage project AH2-374, Richland County
Battery storage project AH2-374, Richland County is a 84.0 MW battery storage request in interconnection study in the PJM interconnection queue, in Richland County, Ohio, connecting to ATSI.
Queue statusIn planning
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH2-374
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Milliron - Brookside 138 kV II
- Location
- Richland County, Ohio
- Technology
- Battery: 84.0 MW
- Total requested
- 84.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 10 March 2022
- Proposed online date
- October 2027
Location
Marker shows the centre of Richland County; the queue data does not give exact sites.
Other requests in Richland County
- Black Fork WindOnshore wind · 200 MW · withdrawn
- Onshore wind project W4-021A, Richland CountyOnshore wind · 200 MW · withdrawn
- Solar project AH1-609, Richland CountySolar · 168 MW · withdrawn
- Solar project AH1-608, Richland CountySolar · 49.3 MW · withdrawn
- Gas project G498, Richland CountyGas · 1.1 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem