Grid connection projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown1,329586.0 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

1,329 projects · page 5 of 27
ProjectCapacityStageConnection siteFrom
Trawsfynydd B Cwmni Egino
Nuclear · Cwmni Egino
940 MWScoping Trawsfynydd 275kV Substation
National Grid (England & Wales)
Nov 2037
Thornton Facility
Solar + storage · Balwen Limited
930 MWConsents Approved Thornton 400kV Substation
National Grid (England & Wales)
Oct 2032
Lacey's Farm BESS
Battery storage · Bluestone Energy Ltd
924 MWScoping South Anglia Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2033
Marchwood
Gas · Marchwood Power Limited
920 MWBuilt Marchwood 400kV Substation
National Grid (England & Wales)
Carrington Power Station
Gas · Carrington Power Limited
910 MWBuilt Carrington GSP (SP Manweb)
National Grid (England & Wales)
Keadby South Power Station
Gas · Keadby Generation Limited
910 MWBuilt Keadby 400kV Substation
National Grid (England & Wales)
Apr 2034
Medway Power Station
Gas · Medway Power Limited
910 MWBuilt Grain 400kV Substation
National Grid (England & Wales)
Oct 2028
Protos Power Station
Gas · Keadby Generation Limited
910 MWScoping Merseyside Connection Node A 400Kv Substation
National Grid (England & Wales)
Nov 2037
Stallingborough Carbon Capture Ccgt
Gas · RWE Generation UK Plc
906 MWScoping Grimsby West 400kV Substation
National Grid (England & Wales)
May 2035
Langage
Gas · Ep Langage Limited
905 MWBuilt Langage 400kV Substation
National Grid (England & Wales)
Elmya Gissing BESS & PV
Solar + storage · Rpc Elmya Carnation Gissing Limited
900 MWScoping North Anglia Connection Node A 400kV
National Grid (England & Wales)
Oct 2034
Fiddlers Ferry BESS
Battery storage · Fiddlers Ferry Ltd
900 MWConsents Approved Fiddlers Ferry 275kV Substation
National Grid (England & Wales)
Oct 2029
Keadby II
Gas · Keadby Generation Limited
893 MWBuilt Keadby 400kV Substation
National Grid (England & Wales)
Keadby North Power Station
Gas · Keadby Generation Limited
892 MWAwaiting Consents Keadby 400kV Substation
National Grid (England & Wales)
Oct 2031
East Anglia One North
Offshore wind · East Anglia One North Limited
880 MWAwaiting Consents Friston 400kV Substation
National Grid (England & Wales)
Oct 2034
East Anglia Two
Offshore wind · East Anglia Two Limited
880 MWAwaiting Consents EA2A and EA2B 275/66kV Offshore Platform
National Grid (England & Wales)
Dec 2030
East Anglia One North
Offshore wind · East Anglia One North Limited
860 MWAwaiting Consents Friston 400kV Substation
National Grid (England & Wales)
Oct 2029
East Anglia Two
Offshore wind · East Anglia Two Limited
860 MWAwaiting Consents EA2A and EA2B 275/66kV Offshore Platform
National Grid (England & Wales)
Mar 2028
Net Zero Teesside Power Project
Gas · Net Zero Teesside Power Limited
860 MWConsents Approved Tod Point 275kV Substation
National Grid (England & Wales)
Jul 2027
Norfolk001
Solar + storage · Epl Newco1 Limited
860 MWScoping Walpole 400kV Substation
National Grid (England & Wales)
Nov 2031
Bradenham - Thetford (Necton) GEC (Ethos Green)
Solar + storage · Necton Green Energy Centre Ltd
850 MWScoping Necton 400kV Substation
National Grid (England & Wales)
Oct 2033
Buntington GEC
Solar + storage · Buntington Green Energy Centre Ltd
850 MWAwaiting Consents Cottered 400kV Substation
National Grid (England & Wales)
Jul 2032
Coryton
Gas · Coryton Energy Company, Ltd.
850 MWBuilt Coryton South 400kV Substation
National Grid (England & Wales)
Oct 2029
Elmya Kilworth BESS & PV
Solar + storage · Rpc Elmya Carnation Kilworth Limited
850 MWScoping Derbyshire Connection Node H 400kV Substation
National Grid (England & Wales)
Oct 2037
Elmya Ryston BESS & PV
Solar + storage · Elmya Energy UK 13 Limited
850 MWScoping North Anglia Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2034
Hockliffe GEC (Ethos Green)
Solar + storage · Hockliffe Green Energy Centre Ltd
850 MWScoping Dunstable 400kV Substation
National Grid (England & Wales)
Oct 2032
Severn Power
Gas · Severn Power Limited
850 MWBuilt Uskmouth 275kV Substation
National Grid (England & Wales)
Sutton Bridge
Gas · Sutton Bridge Power Generation
850 MWBuilt Walpole 400kV Substation
National Grid (England & Wales)
Wilton CCGT Project 1
Gas · Sembcorp Utilities (UK) Limited
850 MWConsents Approved Greystones B 275kV Substation
National Grid (England & Wales)
Oct 2035
Spalding Energy Expansion
Battery storage · Spalding Energy Expansion Limited
850 MWConsents Approved Spalding North 400kV Substation
National Grid (England & Wales)
Oct 2030
Botley West - Cote Solar Power Station
Solar · Solarfive Ltd
840 MWAwaiting Consents Farmoor 400kV Substation
National Grid (England & Wales)
Oct 2031
Woburn Solar Farm
Solar · SolarThree Ltd
840 MWScoping Dunstable 400kV Substation
National Grid (England & Wales)
Oct 2031
Triton Knoll Offshore Wind Farm
Offshore wind · Triton Knoll Offshore Wind Farm Limited
824 MWBuilt Triton Knoll Offshore Substation
National Grid (England & Wales)
Damhead Creek
Gas · VPI Power Limited
812 MWBuilt Kingsnorth GSP
National Grid (England & Wales)
Grantham Solar Farm - RSL
Solar + storage · South Grantham Energy Centre Limited
810 MWScoping Trent Valley South Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Rocksavage
Gas · Rocksavage Power Company, Ltd.
810 MWBuilt Rocksavage 400kV Substation
National Grid (England & Wales)
Botley GEC (Ethos Green)
Solar + storage · Botley Green Energy Centre Ltd
800 MWAwaiting Consents Botley 400kV Substation
National Grid (England & Wales)
Oct 2033
Cliff Hill Energy Farm
Solar + storage · Renewable Energy Systems Limited
800 MWScoping Navenby 400kV Substation
National Grid (England & Wales)
Oct 2034
East Lincolnshire Solar
Solar + storage · Statkraft UK Ltd
800 MWScoping Lincolnshire Coastal Node B 400kV Substation
National Grid (England & Wales)
May 2035
Elmya Foxdale BESS
Battery storage · Rpc Elmya Carnation Foxdale Limited
800 MWScoping Trent Valley South Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Flash Solar Farm
Solar + storage · Elements Green Trent Ltd
800 MWConsents Approved Staythorpe 400kV Substation
National Grid (England & Wales)
May 2028
Hill Street Solar PV/BESS Station
Solar + storage · Hill Street Shelfco 1 Limited
800 MWScoping Staffordshire Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Melksham BESS & PV
Solar + storage · Elements Green Limited
800 MWScoping Melksham 400kV Substation
National Grid (England & Wales)
Oct 2037
Monk Fryston Energy Park
Solar + storage · Elements Green Development Ltd
800 MWScoping Monk Fryston 400kV Substation
National Grid (England & Wales)
Oct 2035
NatPower Hartlepool Green Energy Park
Battery storage · Np Spv 34 Limited
800 MWScoping Wearside Connection Node A 275kV Substation
National Grid (England & Wales)
Oct 2035
Scarning
Solar + storage · Connectid 3 Limited
800 MWAwaiting Consents North Anglia Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Springwell
Solar + storage · Springwell Energyfarm Limited
800 MWScoping Navenby 400kV Substation
National Grid (England & Wales)
Oct 2030
Stockhills Farm
Solar + storage · Bsr Applications Limited
800 MWScoping Severn Connection Node A 400kv Substation
National Grid (England & Wales)
Oct 2037
Sweet Briar Energy Park
Solar + storage · Sweet Briar 2 Energy Park Limited
800 MWScoping South Humber Connection Node A
National Grid (England & Wales)
Oct 2035
Tween Bridge Solar Park
Solar + storage · RWE Renewables UK Solar and Storage Limited
800 MWScoping Trent Valley North Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Page 5 of 27

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.